IIn November 2017, the Neolit Logistics took part and won a tender announced by one of the state enterprises for the transportation of equipment from the main gas turbine unit from the city of Nikolaev to the Odessa port for its further export to India.








For this transportation, 11 oversized platforms were involved, two of which transported equipment weighing 32 tons each.
The task was complicated by a short deadline. All platforms were to follow in one road train under one invoice strictly under the ship’s exit. The risks of force majeure were reduced to a minimum.
4.12.’17 the first seven cars were submitted for loading
5.12. ’17 – the other four, as agreed with the customer. On the same day, customs clearance was carried out.
6.12. The equipment was fully delivered to the administration of the Odessa Sea Commercial Port for export to India.